Progress Report for September 2 – 11, 2015

Exterior of the Admissions and Records building.As students and faculty settled into the rhythm of a new school year, Wireless Expansion and Upgrade work kicked back into full swing, with three more buildings completing their upgrade and four more starting the construction phase in the first two weeks of September.

The Admissions and Records Building, the Armory, and Huff Hall all successfully finished their Wireless Expansion and Upgrade work. For more on what to expect when a building is upgraded, please visit What To Do After Your Building Is Upgraded.

In addition, the Architecture Annex, the Art and Design Building, the National Soybean Research Center, and Turner Hall entered the construction phase of their upgrades.

 